GIF ++ ISD / Safety Clearance
The Initial Safety Declaration (ISD) should be filled out before you move your setup inside the GIF++ facility.
Please complete your ISD form here.
If you have any question, please contact the EP Safety Office at ep-adso@cern.ch.
ISD and Safety Clearance process:
1. Fill in the ISD form
- A proposed time for a safety inspection should be specified
- The IMPACT must be made before the ISD
2. Submit the ISD form
The following email addresses must be provided in order to notify the concerned persons:
- Setup Responsible email,
- Technical Coordinator email,
- Other emails.
3. After the submission of the ISD form
- You will be contacted by the EP Safety Office to confirm the date/time of the safety inspection
4. Safety Inspection
- Please ensure the installation is completed before the Safety Inspection
5. Safety Clearance
- After the on-site inspection, if no major remarks are present, the EP Safety Office delivers a formal Safety Clearance report via email.
- This report might also contain remarks and actions to be done before the start of the operation.
- In certain case, the EP Safety Office might decide to have a second inspection on site to check that all previous remarks have been solved.
To be noticed that any substantial modification to the set-up, implemented after the inspection, invalid the clearance and thus require a new ISD to be filled-in.